Sprint 6 Retrospective

  • Yes, we achieved the Sprint Goal.

  • We completed all features for the MVP and even added some extra features beyond our plan.

What Went Well

  1. The user whitelist access system was successfully implemented.
  2. Added functionality for quiet hours.
  3. The reminder system works according to your time zone.

Problems Encountered & Solutions

Problem 1

  • Limited Number of Developers for Coding

Description

  • Only one team member was able to write code in Python.

Root Cause

  • Other team members did not have enough technical knowledge.

Solution Applied

  • The team is working on improving technical knowledge and skills.

Problem 2

  • Problem: Difficulty Learning New Tools

Description

  • Some tools and technologies were new for the team.

Root Cause

  • The project required tools that were not used before.

Solution Applied

  • The team learned the tools by reading documentation and watching guides.

Changes in next Sprint

Priority Improvement Action Apply
High Increase development speed Split large tasks into smaller ones ✅ YES
Medium Reduce dependency on a single specialist Share knowledge through documentation and internal mini-trainings ✅ YES
Low Improve meeting efficiency Prepare clear agendas and limit meeting duration ❌ No
  • One team member learned how to work with Git by themselves.
  • We also learned what Configuration Management is and how it helps to organize project changes.