Sprint 6 Retrospective
Sprint 6 Retrospective
-
Yes, we achieved the Sprint Goal.
-
We completed all features for the MVP and even added some extra features beyond our plan.
What Went Well
- The user whitelist access system was successfully implemented.
- Added functionality for quiet hours.
- The reminder system works according to your time zone.
Problems Encountered & Solutions
Problem 1
- Limited Number of Developers for Coding
Description
- Only one team member was able to write code in Python.
Root Cause
- Other team members did not have enough technical knowledge.
Solution Applied
- The team is working on improving technical knowledge and skills.
Problem 2
- Problem: Difficulty Learning New Tools
Description
- Some tools and technologies were new for the team.
Root Cause
- The project required tools that were not used before.
Solution Applied
- The team learned the tools by reading documentation and watching guides.
Changes in next Sprint
| Priority | Improvement | Action | Apply |
|---|---|---|---|
| High | Increase development speed | Split large tasks into smaller ones | ✅ YES |
| Medium | Reduce dependency on a single specialist | Share knowledge through documentation and internal mini-trainings | ✅ YES |
| Low | Improve meeting efficiency | Prepare clear agendas and limit meeting duration | ❌ No |
- One team member learned how to work with Git by themselves.
- We also learned what Configuration Management is and how it helps to organize project changes.